Completion of Buckeye Technologies Energy Project Pushed to End of the Year, an Industrial Info News Alert

SUGAR LAND, TX–(Marketwire – March 30, 2010) –  Researched by Industrial Info Resources (Sugar Land, Texas) — Buckeye Technologies Incorporated (NYSE:BKI) (Memphis, Tennessee) has slowed the construction phase of a $45 million energy project at the company’s pulp mill in Perry, Florida. Buckeyes’ Foley Energy Project was previously scheduled to be completed this spring, but is now planned for completion later this year.